Architectural Joinery
The Challenge of St Vincent Street
Sarah Gerrish
| |
 |
|
| |
The pulpit platform, stair and ‘aedicule’ framed doorway (Photo: George Crawford/www.croftglenimages.co.uk) |
|
St Vincent Street Church, Glasgow
was designed by the great Scottish
architect Alexander ‘Greek’ Thomson.
Completed in 1859, it is believed to be his
only intact surviving church and it remains in
ecclesiastical use today. In 1997 the category A
listed church was transferred to the Alexander
‘Greek’ Thomson Trust and was put on the
World Monuments Fund’s watch list of 100
most endangered sites.
Glasgow City Council initiated a
programme of repairs to the church and
Page & Park Architects was invited to prepare
proposals and a specification for the works,
which included essential repairs to the
roof. Conservation works to the tower were
completed as phase one in 2000, with phase
two of the conservation work, dealing with the
main and side aisle roofs, also now complete.
In 2007 Sarah Gerrish Conservation was
approached by Page & Park Architects to act as
a consultant advising on the treatment of the
historic wooden interior of this unique church. To facilitate the roof works, which
required the structural reinforcement of the
three roof trusses, an internal scaffold was
needed to provide access to the perimeter of
the three main timber roof trusses and to
provide temporary support for each of the
trusses while repairs were carried out to the
truss ends. The main contractor gave careful
consideration to the design, installation and
type of scaffolding to be used in this process.
Practical constraints were balanced with the
need to preserve the interior as far as possible.
To allow the scaffold to be constructed,
some of the pews and floorboards on the
ground floor and gallery level had to be
removed to allow the scaffolding poles to
pass through to the undercroft below. It
was necessary to remove the undercroft
ceiling and take up the undercroft
floor to allow the scaffolding poles to
be sunk into the ground beneath.
Although the church’s original woodwork
looked robust, it was highly vulnerable
and care was taken at every stage of the
conservation process to ensure progress
was maintained at a slow and steady pace.
THE CONSERVATION APPROACH
The approach at St Vincent’s emphasised
conservation rather than restoration. The aim
was to preserve and stabilise as much of the
original wood as possible using treatments
that are technically reversible. This means
using only materials that have been thoroughly
researched and tested so that their behaviours
in different environments can be predicted.
Furthermore, it should always be possible to
remove or ‘reverse’ a treatment at some point in
the future without causing undue damage to the
original artefact, if a better conservation method
or a more appropriate material is discovered.
| |
 |
|
| |
The interior seen from gallery level (Photo: Phil Sayer, licensor www.rcahms.gov.uk) |
|
Documentation is another key aspect
of the conservation approach, including
condition surveys, treatment reports and
photographic documentation showing the
artefact before, during and after treatment.
These records also enable conservators
working on the artefacts in the future
to establish how best to proceed.
While the principles of conservation
governed all aspects of the work at St Vincent’s,
the complex nature of the roof works dictated
a more invasive approach to the architectural
joinery of the interior than would ideally be
chosen. The timber conservation proposals
(outlining what was to be done) and method
statements (outlining how it was to be done)
ensured a minimally interventive approach
for the long term protection of this historically
important interior and its furnishings.
AGENTS OF DETERIORATION
A crucial element of the conservator’s task is
protecting fabric and artefacts from identified
agents of deterioration. The agents affecting
timber commonly include:
- sunlight (UV radiation)
- physical or mechanical damage
caused during handling and cleaning,
or by acts of vandalism, etc
- biological decay caused by fungi
(dry rot for example) and insects
(woodworm for example) etc
- environmental damage such as warping and
splitting joinery, due to movement caused
by high, low or fluctuating temperature,
and changes in relative humidity
- water damage caused by leaks, spillages, etc
- fire or smoke damage.
There was no evidence of insect damage or rot
in the pews and floorboards at St Vincent’s,
although in many places the roof had been
leaking for long periods of time. However,
the patina and surface finish of the pews
had suffered water damage in places from
prolonged leaks in the ceiling.
THE PULPIT PLATFORM
In order to provide a method statement for
the removal of the selected timber elements,
it was necessary to understand how they had
been constructed. The scaffold was designed
to minimise disturbance to the existing
architectural joinery. However, due to practical
constraints, the timbers along the front line
of the pulpit platform had to be removed. The
platform has steps on either side leading up to
the pulpit, and the bottom step was removed
to allow five scaffold poles to pass through into
the undercroft below.
| |
 |
|
| |
Internal scaffold in front of the organ and the pulpit |
|
By crawling into the cavity under the
platform it was possible to examine the
construction and decide how best to remove
the step. It was important to try to remove
it without having to dismantle the whole
structure. The carpet was carefully rolled
back to reveal the steps, which were built
on a wooden framework to which the treads
and sides were nailed. Having marked the
floorboard to be lifted it was possible to push
the board up from the underside to ease it
upwards. From the outside of the platform
the nails securing the boards to the frame
were cut along the front edge where the step
met the riser using a very fine toothed saw
and taking care not to mark the wood.
From underneath the platform, wedges
were hammered in to lift the boards and the floorboard was prised from above at
the same time using blocks, taking care not
to bruise the front of the boards. Working
systematically from above and below in this
way along the length of the board ensured
even lifting and prevented the board from
splitting. At the mitres, the pins holding the
boards down were punched through using
a nail punch, which enabled the board to be
gently prised up from the upper surface and
wedged from underneath for an even lift.
Once the board had been removed, the
framework of joists under the platform was
exposed. It became clear that one element of
the joist lay in the path of one of the scaffold
poles. It was not possible to remove the
joist to allow the scaffold poles a free path
without dismantling the whole framework
and platform above, which was considered too
invasive and not feasible. The organ had also
been built into the platform, so this structure,
built in 1904, would have had to be removed
too. The solution, although not ideal, was to
cut a notch out of the joist and to retain the
piece to re-fit after the works were completed.
The floorboards running under the
platform and pulpit appeared to have no
joints in them where the boards to be
removed were located. The platform was built
over the floorboards, which should ideally
be lifted at a natural joint. However, this
too would have involved dismantling the
platform so it was necessary, using a very
fine toothed Japanese saw, to cut a section
of floorboard to enable the scaffold pole to
pass through, the pieces were retained to
be replaced after removal of the scaffolding.
The floorboards in this area are not usually
seen as they are located under the platform.
THE GALLERY
| |
 |
|
| |
Gallery fascia with cast-iron column capital (Photo: George Crawford/www.croftglenimages.co.uk) |
|
The scaffold poles also had to pass through
the gallery, which involved removing one row
of pews and the floor so that a core drill could
be used to pierce the floor of the gallery and
the plasterwork ceiling, allowing access for the
scaffold poles. Initially, it was thought that pew
number 127 would have to be removed from
the gallery along with the floorboard beneath
it. The pews were jointed into the floor so
it was necessary to remove the floorboards
before the pews. The pews were built into a
wooden framework that runs under floor level.
They are an integral part of the construction of
the tiered gallery and the floor and so it would
have been a major operation to remove the
pew without interfering with other structures.
Ultimately, after very careful measurement
and consultation of the scaffold plans, it
proved possible to remove the floorboards
and construct the scaffold without removing
pew 127.
The implications were double-edged: unnecessary dismantling of the pews was
prevented but the scaffolders would have to
be very accurate when locating the required
five poles as they would only have the smallest
possible hole through which to insert the
long poles.
It was suggested that a jig should
be used to help with the pole location
because if the poles were to slip, damage
would be caused to the wooden structures
and plasterwork. The floorboard consisted of
one long run so the five poles were located
in that area to prevent the need to lift any
further floorboards on the curved sections
of the pews. The pew’s book-rest was very
near the area where the poles penetrated so
it was necessary to protect the book-rest and
back of the pew while the scaffold was erected
using plywood sheets and bubble wrap.
THE PEWS
Five pews in the main body of the church
had to be removed to allow the scaffold to be
erected. From surveying the existing pews it
was determined that every second leg support
of the pews was nail fixed through the flooring
to the joist below. Using hardwood wedges
each leg support was carefully released. The
centre joint of the pews was butt jointed with
timber dowels. Using the same method with
wedges, one side of the pew was released
and then, by moving the pew sideways, the
dowelled joint was freed. The left hand section
of the pews, facing the front of the church, also
had a central mortise and tenon joint. Once the
pew was free from its leg fixing, the mortise
and tenon joint could be freed.
ENVIRONMENTAL CONDITIONS
Once removed, the pews were carefully packed
in bubble wrap and stored at the back of the
church. It was decided not to remove them for
several reasons, principally because placing
them in storage would have meant exposing
them to a different set of environmental
conditions that could have adversely affected
them. The ideal conditions for the woodwork
would be a temperature of 18-20°C and relative
humidity of 50-55 per cent plus or minus 5 per
cent.
While the church itself does not
present ideal environmental conditions (it
is quite cold and damp during the winter
months) it is the fluctuation of temperature
and relative humidity that is especially
damaging, potentially causing wood to
shrink, split or warp. Transporting the pews,
which are over 20 feet long, would also
have been both awkward and unnecessary.
The more artefacts are handled the more
likely it is that they will incur damage.
REPLACING THE HISTORIC TIMBERWORK
All fixings were retained during the removal
of the pews and floorboards and, wherever
possible, these were re-used in the original
fixing holes to avoid drilling into original
timber unnecessarily. The brass umbrella
stands and holders attached to the pew ends
were removed and labelled before they were
dismantled and the screws retained to ensure
that they were replaced on the correct pew and
using the original fixings on completion.
All the elements that were removed
to enable the scaffold to be built were
carefully labelled and wrapped and
care was taken to replace them in the
correct aspect on their return.
| |
 |
|
| |
Thomson's elegantly curved pews
(Photo: George Crawford/
www.croftglenimages. co.uk) |
|
Every effort was made to protect the pews,
pulpit/organ ensemble and other wooden
elements that remained in situ throughout
the works by encasing them in free-standing
plywood boxing and plastic sheeting to
protect from building dust and mechanical
damage. Nevertheless, it was inevitable that
the woodwork became very dusty. Proposals
were drawn up for cleaning the woodwork that involved vacuum cleaning all excess dirt and
dust, a controlled wet clean, tinting in areas
which had been water damaged, and protecting
the woodwork with wax polish. The protective
boarding covering the pews and scaffold planks
were all vacuumed before disassembly to
prevent building dust falling onto the historic
woodwork as per the recommendations. The
main contractor undertook the responsibility
for the basic cleaning of the wooden
elements after the scaffold was removed.
CHALLENGES AND REWARDS
Typically, the conservation of historic interiors
is carried out in a complex and sensitive
environment. The conservator has to work
around the tight limitations imposed by the
need to minimise the risk of harm to a large
and diverse range of historic artefacts and
fabric. Intervening to conserve one element
of a historic interior, like the woodwork at
St Vincent Street, often threatens to impact
on a host of others, all equally deserving of
respect. Conserving sensitively and responsibly
under these conditions can be enormously
challenging, but the rewards for all concerned
are every bit as great.
~~~
Recommended Reading
- R McFadzean, The Life and Work of Alexander
Thomson, Routledge, London, 1979
- G Stamp, Alexander Thomson: The Unknown
Genius, Laurence King Publishing in
association with Glasgow 1999 Festival
Company Ltd, London, 1999
- G Stamp and S McKinstry, ‘Greek’ Thomson,
Edinburgh University Press, Edinburgh,
1994
|
|
The Building Conservation Directory, 2011
Author
SARAH GERRISH ACR is an accredited
conservator and has been practising for
20 years. She has worked for the National
Museums and Galleries of Wales and National
Museums Scotland as a furniture and wooden
artefacts conservator and now runs her
own business, Sarah Gerrish Conservation,
from her workshop in Edinburgh.
Email
sarahgerrishconservation
@hotmail.co.uk.
Further
information
RELATED
ARTICLES
Churches (general)
Joinery and cabinetmaking
Wood
RELATED
PRODUCTS AND SERVICES
Fine joinery
Timber repairs
Timber suppliers

Site Map
© Cathedral
Communications Limited 2011
|