Mortar & Steel
Katie Worthington outlines techniques for fixing fine stone carving repairs to structures
The finely
carved stonework of capitals, cornices and other architectural
enrichments often needs some carefully executed repairs. As originally
constructed, these elements form the visible face of large stone
blocks which extend back into the face of the wall or column.
However, when repairs are carried out, it is rarely practical
or acceptable to dismantle large sections of the structure just
to replace lost or damaged surface decoration. As a result, new
carved elements must be pieced in and secured to the block behind
soundly and safely so that they do not fall, and discreetly, so
that the repairs do not distract from the visual integrity of
the design. Heavy new pieces of carved stone decoration sometimes
project out over public spaces, adding additional structural concerns.
Before cutting
out any eroded stone the restoration process must be discussed
between the architect, the main contractor and the carver or mason
responsible for carrying out the work. The next step is to produce
a method statement explaining the repairs and how they will be
carried out safely and in accordance with the requirements of
the building, taking into account such considerations as the need
for historical accuracy and the retention of important fabric.
Whether re-carving whole capitals or smaller decayed or damaged
sections in churches or other historic buildings, good planning
is as essential as the use of carefully considered and established
masonry techniques.
One of the
first aspects to be considered is the extent of the deterioration
and the quantity of stone lost due to weathering and incidental
damage. An experienced carver may design the restoration to include
what is known to have been there originally, based on surviving
surface profiles and other evidence. However, speculative restoration
should always be avoided as it is essential that the repair is
historically accurate, and structural concerns are equally important.
As well as
being involved in the initial discussion, it is essential that
the same carver or mason is employed throughout. This allows the
mason to tailor each stage to suit the project, from assessing
the original design and its condition during the initial cutting
out of the eroded stone, to fixing the finished piece. In this
way seamless adjustments can be made at each step, to respond
to any information uncovered.
|
|
(top)
detail showing the horizontal notch at the back of the opening
and (middle) the new stone fixed in position pending carving
(below)
(Photos: Katie Worthington by courtesy of Stonewest
Ltd) |
|
|
It is possible
to break a typical project down into three distinct elements:
the cutting and carving of the feature, the logistics of moving
the replacement stone, and the secure fixing of the item into
place as part of the building's fabric. The following cases illustrate
how typical problems associated with these elements can be overcome
in practice.
A
CAPITAL AT ST PAUL'S
The re-carving
of a section of a Corinthian capital at St Paul's Cathedral presented
many problems, partly due to the sensitivity of the structure,
which, as a Grade I listed building, demanded the highest standards
of carving as well as the retention of as much of the original
carvers' work as possible. The very public location and height
of the scaffolding also presented some interesting challenges.
Work began
with the cutting open of the original capital to discard badly
eroded stone. Up close it was possible to see the original geometrical
setting out lines, still scribed on the stone. In order to save
as much historic fabric as possible, only a wedge of badly weathered
material was removed, instead of the capital being sliced in half.
A replacement piece of stone was then roughed out to the approximate
shape of the capital to reduce its weight. This was placed on
a bogey and moved by a team of masons up the tower of the cathedral
via scaffolding and a hoist. The most difficult part of the route
was then to push the stone up and over the v-shaped rooftop before
it could be lifted up into the south west bell tower. The route
required careful thought and preparation, since any protrusions
and traps in the supporting scaffolding could have halted progress
and caused a serious safety hazard.
The fixing
of this capital had many complications. In particular the replacement
section was top heavy and inclined to tilt forward. However, by
accurately cutting the stone and leaving only narrow gaps for
mortar beds (in this case 5mm) tilting could be prevented, as
the stones above it and below would trap it in position once it
was in place.
In order
to create as secure a fixing as possible, a horizontal notch was
cut into the back face of the opening to help interlock the new
stone with the existing structure. In addition, stainless steel
316 grade threaded dowels were used to pin the new stone in place.
The dowels were secured by drilling three dowel holes, two at
the top and one at the bottom in the back face of the existing
capital and the new section of stone, so that the holes could
be accurately aligned when the two sections were joined together.
After clearing the dowel holes of dust, they were filled with
an epoxy resin. The stainless steel threaded dowels were then
quickly inserted into the dowel holes of the existing capital.
Time is of the essence as the resin can set in as little as five
to ten minutes in hot weather.
The stone
then had to be 'keyed up', a process which gave it extra grip.
This involved making cuts with an angle grinder (traditionally
a hammer and chisel would have been used to create pits and punch
marks) on the adjoining joints into which the mortar engages itself.
A bed height of 5mm was prepared using a 'St Paul's mix', a proprietary
mortar which sets hydraulically - that is to say, without the
need for air - enabling it to set deep within the structure where
there is insufficient air for lime to carbonate. (Ordinary non-hydraulic
lime mortars need atmospheric carbon dioxide to set.) It also
increases the strength of the mortar, enabling it to take the
weight of the stone in compression without any large aggregate
particles.
Once this
process was completed, three masons lifted the stone with the
aid of a block and tackle and straps, and rolled it into location
on 5mm stainless steel dowels, thus ensuring sufficient space
for the mortar bed. The stone was then grouted.
Grout is essentially
a fluid mortar designed to fill voids and bed joints. It is absorbed
by the new and old stone, keeping them apart. When set it remains
softer than the stone and retains some plasticity to allow for
some structural movement in the building. The grout used at St
Paul's was a hydraulic mixture containing bentonite, a clay mineral
which made the grout more fluid.
 |
|
 |
|
 |
|
| An
indent repair at the Royal Pavilion, Brighton, showing the
hole in the underside of one of the palm leafed capitals after
cutting out the damaged section (top) and the repair (middle).
The detail (bottom) of the work before pointing shows more
clearly that the lines of the new work copy the lines of the
original carving, and are slightly proud of the weathered
surface above |
|
Before grouting
was carried out, the new stone was secured with wooden wedges
which had been soaked in water to swell the wood, and the joints
were pointed with mortar. Once this had set, the grout was poured
into a hole left at the top of one of the joints though a funnel
(actually half a plastic cup fixed temporarily to the wall using
mortar), keeping one eye on the joints below in case a leak occurred.
Pouring continued steadily until the grout filled to the top of
the hole. Later, after the wedges had dried out, it was possible
to remove them easily, without disturbing the stone.
THE
CAPITALS OF THE ROYAL PAVILION, BRIGHTON
The Royal
Pavilion is constructed with soft Bath stone. Due to its close
proximity to the sea, its exterior is attacked by salt-laden sea-spray
which is driven into the stone. This accelerates its decay, resulting
in the need for frequent repairs. A lot of indent work was needed
to cut out small sections of deteriorating stones, and in some
cases whole stones had to be replaced. Work on this project proved
to be as complex as the architecture of the building.
The corroded
stone was carefully cut out with an angle grinder and finished
by hand tools so as not to damage the surrounding stones. This
enabled straight lines to be produced between the leaves, aiming
to be symmetrical where possible and 'level', while following
their general shape. The resulting indent was shaped like an inverted
triangle, with the point at the bottom.
In this part
of the facade the decorative leaves on the fanned capitals were
designed to imitate those of a palm tree, giving them an intricacy
that made restoration work more complicated. In this case the
indents were small, so sections of plain stone could easily be
lifted by hand and slotted into the cut-outs once they had been
shaped to fit. By finishing the stone on the spot it was possible
to get really tight joints of no more than 2mm, as specified by
the architects.
After securing
the stone in position, leaf shapes were drawn directly onto its
face, accurately following the shape of the surrounding leaves,
and these shapes were then carved in situ. Because of their palm
tree form, the Royal Pavilion's stone leaves fan out vertically
and are fuller at the top, so the tips of the leaves are bigger
than the bottom. They loosely resemble an inverted triangle, although
the edges of the leaves are rounded and contoured.
In order
to ensure accuracy, one method that can be used for this kind
of work is to employ templates made on plastic template paper,
to transfer cross sections of the design onto the stone being
worked. Whatever means are employed, it is essential that work
is thoughtful and accurate, not only for aesthetic reasons, but
also because restoring a block of stone or carved element to its
original size can mean that it protrudes from the surrounding
weathered stone, putting it at a greater risk of erosion and giving
it an incongruous appearance.
In the case
of the Royal Pavilion stone, the triangular-shaped indent described
above reduced the amount of stone sitting in the wall on top of
the bottom stone. So, as a measure of security, a long stainless
steel threaded dowel was placed through the back of the stone
deep into the wall, while another dowel was 'moused' in the vertical
joint. Mousing is commonly used for fixing stones through the
vertical joints where one stone cannot be placed on top of another
(as in the case of the finial capitals in London city cemetery,
right). Mousing may also be required when fixing onto a horizontal
bed. The process involves sliding the dowel fully into one stone
with a piece of string (the mouse's tail) tied to the end of the
dowel that is furthest in the hole. When the stone is put in place,
pulling the string causes the dowel (the mouse, so to speak,)
to slide back out across the joint into the adjacent hole.
 |
 |
| Detail
of the new carving and its back after being 'keyed up' with
an angle grinder (Photos: Katie Worthington, by courtesy of
Stonewest Ltd) |
The process
is not as easy as it sounds. In this case, after preparing aligning
dowel holes, it was essential to ensure that there was enough
room to slide the dowel back into the stone so that it disappeared
and did not get in the way when putting the stone in the wall.
A thin piece of string was tied onto the end of the dowel, taking
care to ensure that it would be long enough to be free of the
joint and adjoining stone once installed. The holes were filled
with epoxy resin and any voids at the back of the stone were filled
with mortar and lime for a 2mm tight joint. The stone was then
placed in situ and the string pulled. Finally the dowels were
checked to ensure that they had located properly. An experienced
mason can do this by sliding a fine blade between the stones and
gauging the feel of the dowels.
OTHER
CASES
 |
 |
 |
Details
of the buttress repairs at Moulton, simply
fixed with mortar
joints and stainless steel dowels
between blocks, and interlocked
with the existing stonework behind to prevent it toppling
forward
(Photos: Katie Worthington, by courtesy of CEL Ltd) |
Of course,
not all jobs are as tricky as those at the Royal Pavilion or St
Paul's. At the parish church of Moulton in Lincolnshire, for instance,
fixing the new carved stonework for the buttresses was fairly
straightforward. Originally constructed with simple, square joints,
the buttresses comprised of three gable stones sitting on a large
bottom bed and attached to the wall behind, with a free standing
finial on top. As a result there was room to move the angle grinder
freely from left to right when cutting out the badly weathered
and crumbling stonework, unrestricted by stones on either side.
It was then simply a matter of reconstructing it using new carved
replacements placed one on top of another, with the aide of a
block and tackle for the heavier stones.
 |
| A
finished finial in position at London City Cemetery (Photo:
Katie Worthington, by courtesy of Stonewest Ltd) |
Finials are
even easier to repair or replace, as they are completely free
standing with no stones on top or, in most cases, surrounding
them. When fixing the finial capitals in London City Cemetery,
for example, it was possible to hold the finial above a dowel
(already fixed to the top of the adjoining pier stone) and slide
down. As these finials were small in size they required only one
pin in the centre - in this case a stainless steel threaded dowel
fixed in epoxy resin.
Each case
needs to be considered individually. A solution which applies
in one case will not work in another, but the principles remain
the same: alter as little as possible; and ensure structural integrity.
|
|
This
article is reproduced from Historic
Churches, 2006
Author
KATIE
WORTHINGTON is an architectural stone carver, mason, sculptor
and letter cutter. She runs Worthington Stone Carving and has worked on many listed
buildings around the UK including York Minster (where she
completed her two-year apprenticeship), St Paul's Cathedral,
The Houses of Parliament (as a Stonewest employee), and the
Royal Pavilion, to name a few. Plaques carved by her have
been unveiled by the HRH Duke of York and the Lord Mayor of
London among others.
Further
information
RELATED
ARTICLES
Statuary and stone carving
RELATED
PRODUCTS AND SERVICES
Sculptors
and stone carvers
Masonry
services (stone masons)

Site Map
© Cathedral
Communications Limited 2010
|