|
The
Chimneys of Lavington Manor
Jarrod
Hill and Rob Thomson
Lavington
Manor, Wiltshire, was completed in 1865 for Edward Pleydell-Bouverie
(1818-1889), fourth Earl of Radnor and Member of Parliament for
Kilmarnock, for the sum of £67,000. The designer was Ewan Christian
(1814-1895), a respected architect of the Church Commissioners,
later president of the RIBA and Royal Gold Medal winning designer
of the National Portrait Gallery in London.
Rambling Tudor in
style, the house has stout diaper-patterned brickwork facades
with Bath stone features and dressings, surmounted by a steeply
gabled and parapeted, polychrome Cornish slate roof. The building
is topped by 11 fine decorative chimneys incorporating differing
relief motifs, enrichments and monographs. These chimney stacks
are constructed with cantilevered geometric brick crowns of an
intricate, holly-leaf plan form, on unique circular, octagonal
and composite shafts comprised of large brick blocks.
 |
| Lavington Manor, Wiltshire |
DEFECTS
By 2005 the
building was exhibiting typical signs of 140 years of weathering,
including decayed mortar joints. Several of the chimney stacks
were in need of comprehensive repair and the slate roof coverings
needed to be replaced. Close inspection during a condition survey
revealed that the chimney stacks were actually unstable and prompt
action was needed to make them safe. Agreement was reached with
the local authority for emergency works and three of the chimneys
were immediately taken down following measurement and photographic
recording. The units were individually marked to record their
location and orientation in the structure and were set out from
the disassembled chimneys at ground level by course and stack,
for each block and brick to be scrutinised for defects. One chimney
had partially collapsed before this process was complete, making
the job of piecing together the units for this composite chimney
extremely difficult. It was, in all, a 2,500-piece jigsaw.
Typical
chimney defects were observed arising from wind loading, wetting
and drying cycles, poor earlier repairs with inappropriate mortars,
sulphate decay from flue gasses, frost action and differential
weathering of the softer blocks. Some of the voids in the redundant
flues were large enough to provide good bat roosts.
Although it
was most unfortunate that it was not possible to repair all the
chimneys in situ, taking three of them down provided the opportunity
to study their construction and gather valuable information for
their repair, which would not otherwise be evident. For example:
- It was discovered that the crowns contained a total of 18 different
brick sizes over 12 courses. When CAD drawings were overlaid to
compare these with the coursed units on the ground, it was evident
that even this number of brick types was insufficient, and two
particular forms needed to complete the bonding pattern had been
missed out, resulting in a historical ‘fudge’. The problems were
compounded by the later reconstructions, which relocated bricks
within the crowns. The two missing units were subsequently commissioned
to complete the scheme.
- The bonding plan was found to be poor,
particularly on the composite chimneys with incomplete octagonal
and circular shafts. This was remedied with stainless steel bed-joint
reinforcement and simple brick repair techniques to the core.
- A consistent pattern of vertical stress failure was evident
parallel to the face of the large clay units, which connected
the weaker ‘necks’ between perforations – effectively making the
blocks two separate units. In addition, vertical cracking was
evident where one portion of the brick had been restrained by
adjacent masonry and the other free to move. In some cases these
were pinned and elsewhere reinforcement was carefully inserted
into bed-joints to stiffen those chimneys which remained intact.
- The perforations of the blocks were un-grouted, leaving substantial
voids for water retention throughout the structure and reducing
the potential strength of the chimneys. The different grain, density
and fissures in the block also aggravated decay by frost action.
MATERIALS
AND PRODUCTION
 |
Bricks from the 'holly leaf' crown of one of the chimneys showing typical deterioration |
The
materials of the chimneys were entirely local. Gault clays, which
form the edge of the Salisbury Plain, were used by Holloway Bros
(formerly Fox) at their local brickworks at Market Lavington.
Lime came from Broadwell Kiln and aggregates from the adjacent
greensand belt.
The local greensand mortars are typically very
soft with a poor matrix of small spherical aggregate, and ordinary
non-hydraulic lime is insufficiently durable for such an exposed
location. As a result, most chimney joints had extensively weathered
or had completely washed out. Clearly an ongoing problem, earlier
campaigns of repair undertaken with thinly applied cementitious
mortars had only aggravated the situation, leaving the joints
with a brittle outer shell but little strength. Frost ‘jacking’
as trapped moisture expanded and contracted with the freeze-thaw
cycle had caused the crown of one stack to shift almost 150mm
(six inches) and corrosion of iron bed-joint reinforcement had
made some chimney sections extremely unstable. During the 1950s
several crowns had been re-built and one of the chimneys had had
three of the shafts replaced with plain brickwork.
The chimney
crowns comprise pentangle and bow-tie shaped bricks of varying
height up to 400mm (16 inches) in length. The shafts contained
200mm (eight-inch) thick blocks of 300mm (12 inches) in height
by typically 500mm (20 inches) in length. Manufacture of these
larger units must certainly have tested the traditional brick-making
techniques of the day and certain problems which demonstrate this
are present on the chimneys.
The clay for larger, complex shaped
units was thrown in several ‘handfuls’ rather than (as with a
regular brick) in one go. Where, for example, clay was poorly
blended (hard work by hand) or the clay was dry (not uncommon
during a summer brick-making season), this could lead to seams
of differential moisture content in the clay ‘loads’. Poorer workmanship
could also have led to other problems including air pockets, unstable
stone inclusions and variation in the grain of the fired clay
where laid from different directions. Decorative detail on the
mould face required clay to be very well pressed in when throwing
the brick into the mould, whereas less force may be applied to
the subsequently placed ‘loads’ causing variation in density and
strength characteristics within the brick.
During drying, ‘green’
bricks can change shape and shrink differentially, so to aid stable
drying and firing larger units are usually made with holes or
voids through their core to increase the proportion of surface
area and reduce the overall mass of the clay. However, with larger
blocks this is hard to perfect and the span and height of units
inevitably means that in some places the clay is much thicker
than others. It is no doubt for this reason that the larger bricks
found at Lavington have up to three holes of varying shapes, created
with a tool similar to an apple corer and routinely cleared by
hand. This action often dragged inclusions to create depressions
and exposed the seams and air pockets discussed above.
 |
| A repaired brick stack |
The temperatures
in traditional clamp and up-draught kilns typically vary from
750oC to 1,200oC, so larger brick units were normally produced
in a down-draught kiln which achieved the more even and consistent
heat needed. Nevertheless, fluctuations in temperature were common
and variations in quality were inevitable. Lighter coloured units,
in this case those with a more orangey colour, generally indicate
a softer ‘fireskin’, which is the dense protective surface of
a brick caused by the partial vitrification of finer particles
during firing. Bearing
in mind that the core of any brick will be less well burnt than
the brick face, the core of these lighter coloured units will
also be weaker and more vulnerable to frost as a result. Those
which were exposed to too great a temperature could, on the other
hand, suffer from too much vitrification, making them brittle.
These characteristics, along with the differential densities,
grain and inclusions of the brick units compromised their ability
to cope with mechanical strains typical in a chimney stack.
CHOOSING
NEW TERRACOTTA
As the original
brickworks was no longer in operation and the local clay is no
longer extracted, new special bricks for the repairs were sourced
from a good geological match, produced by the Pitsham brickworks
of Lambs Bricks & Arches in the traditional manner.
Any decision
to vary the material or technique employed in the repair of historic
fabric should never be taken lightly. However, for the larger
brick units, changes in manufacturing techniques and a better
understanding of the defects required the producer to reconsider
the method for producing new units for the repair, and terracotta
manufacturing techniques were employed which offer considerable
benefits for units of such size:
- matching clays could be well
blended and thoroughly screened to eliminate inclusions which
could split the unit during firing
- the clay could be built up
incrementally, in small quantities, and well pressed into a two-part
moulds, thus avoiding the laminations and grain evident from larger
quantities of thrown clay
- computer controlled drying and firing
ensured dimensional stability and allowed for a more consistent
and controlled kilning
- accurate predictions could be made about
the shrinkage and movement during manufacture, and consistency
of supply for a large number of units is achievable.
Nevertheless,
the brick units from the existing chimneys characteristically
vary individually in dimension and appearance (not only in strength
and performance) and these valuable qualities require consideration
in any new work. By comparison, one downside with new terracotta
production is that these variations are less desirable, and manufacturing
subtly different moulds for each block was not feasible in a small
project such as this. As a result the quality of the new blocks
are more uniform and regular than the original, but they retain
significant similarity.
CHOOSING
NEW MORTAR
The existing
mortar with which the chimneys had been built had all but disappeared
in many areas, leading to 100 per cent repointing on some of the
chimneys that were not dismantled. Two different pointing mortars
needed to be devised that matched well with the existing mortar
but that should give an appropriate level of both strength and
porosity. An improvement was needed on the purely greensand mortar
that had originally been used. The mortar for the vertical sections
of the chimneys was created using English weakly hydraulic lime
(NHL2) from Hydraulic Lias Limes with a mix of Warmwell grit sand
as the main aggregate, and greensand stone dust (from Wessex Dimensional
Stone) as a finer aggregate and for colour. The crowns of the
chimneys were felt to be particularly vulnerable, given the dramatic
nature of their cantilevered construction, so for these the weakly
hydraulic binder was replaced with a French strongly hydraulic
lime (NHL5) from St Astier. It was felt that this would impart
greater strength to this more vulnerable part of the construction.
On balance, any disadvantage caused by the more regular appearance
of the new bricks is minor. Close inspection will, in the future,
clearly reveal which elements are new, and no attempt has been
made to deceive. Through careful refinement of the traditional
brick manufacturing techniques, and reconstruction using sensitive
details and more durable hydraulic lime mortars, these chimneys
are likely to last for many years in the future.
|
© Cathedral
Communications Limited 2009 |