|
The
Reconstruction of Coombe Cliffe Conservatory
Geoffrey
Wallis

This
fine example of Victorian modular construction using high quality
decorative cast iron components was originally built as an attached
extension to the Horniman family house at Coombe Cliffe, Croydon,
in 1894. The castings in grey cast iron were from the then prolific
output of Walter Macfarlane's Saracen foundry in Glasgow, incorporating
the extensive detailed decoration which is typical of this 'Victorian
wedding-cake' era. Features included columns over seven metres long,
cast in one piece, numerous highly decorated ventilator panels, and
curved 'fish-scale' glazing. These delicate iron frames held tiny
panes of flat glass in tiers at slightly differing angles to give
a wonderfully scintillating effect in the sunlight.
By
the time the house at Coombe Cliffe was acquired by the GLC in 1982,
the conservatory had fallen into disrepair. The structure was therefore
totally dismantled and the loose components were deposited in two
open compounds situated, by ironic coincidence, on the site of the
old Crystal Palace, where they remained forlornly abandoned for several
years.
The
unique historical and architectural value of the structure however,
had not been disregarded. Following the closure of the GLC, the project
was taken up by the newly formed London Division of English Heritage
and the Inner London Education Authority, who took the decision to
re-erect the conservatory on a site adjacent to the Horniman Museum
buildings at Forest Hill. No original drawings existed and no structural
dimensions or component identifications had been recorded before dismantling,
although some photographs were available. Painstaking detailed research
and dimensioning of the components at the Crystal Palace was undertaken
by English Heritage architects who also produced drawings for the
re-erection of the structure.
As
specialists in the field, the Bristolbased Southern division of Dorothea
Restorations Limited was awarded the contract to restore the ironwork
and re-erect the building. The project presented a significant problem
in managing hundreds of random components which were lying in the
Crystal Palace compounds, partly hidden by undergrowth. A system was
devised using specially printed record sheets with a separate sheet
for each component giving its description, its part identity number
(derived from its position in the building), its condition as found
and the repairs required. The sequence and nature of each repair operation
was recorded, with details of grit-blasting and painting requirements,
requirements for patterns and replication castings, and transportation
details. These sheets were incorporated into volumes to provide a
comprehensive schedule which was updated on a daily basis providing
the repair status of every component and its whereabouts throughout
the programme. Typical entries might include; 'at foundry Bristol
as pattern for NA6', 'at Metalock for stitch repair', 'at DRL Whaleybridge
for weld repair'. Only in this manner could it be ensured that no
components were lost and a full complement of parts would be available
for the recreation programme.
The
specification required all components to be grit-blasted clean and
immediately primed with two coats of 2 pack epoxy primers. Some major
components such as main arches and columns weighed up to a ton and
therefore required careful and cautious handling within the restricted
confines of the Crystal Palace compounds, to gain all-round access
for blasting and painting. No components were fractured or damaged
during the preparation, repair, or re-erection programme.
Hundreds
of individual repairs were required; many were minor fractures in
dado panels, frieze panels or the fishscale frames of the curved roof
windows which could be satisfactorily arcwelded on site. But there
were also a large number of extended longitudinal fractures, usually
in the hollowbore rainwater columns, which required metalstitching
repairs over lengths up to 4 feet (1.2 metres).
Originally
the conservatory was butted up against the wall of the main house
at Coombe Cliffe, and did not include an east wall. It was therefore
necessary to replicate a complete new outfit of castings for columns,
beams, friezes, dado panels and window frames using the west wall
components as the pattern and adapting as necessary to give the correct
handing and dimensions. Two of the four columns supporting the central
tower structure required lengthening by 30 inches to suit floor levels
at the new site. These columns are of a four-start barley sugar twist
cross-section which presented problems in the production of helically
matched moulds, patterns and castings, as the extensions had to be
both structurally sound and visually continuous with the original
barley twist when they were fitted and stitched to the original columns.
A multiplicity of smaller castings for window mullions, transoms and
glazing bars were produced to replicate missing parts and those beyond
economic repair, together with small elements of scrolls, finials,
acroteria and miscellaneous decorative items which were necessary
to give a visually complete detailed structure.
The
re-erection process was complicated by the lack of original component
identification and thus beams, columns and arches came together in
the rebuild, although they had not been related, drilled and fastened
together in the original structure. Particular attention was therefore
necessary when adapting old fastening holes to achieve true structural
levels, verticality, and alignment integrity in the resurrected building.
Similar problems were inherited in the erection of the minor outfitting
components such as dado panels, friezes and window frames, and the
alignment of the in-built glazing landings had to be constantly borne
in mind. This requirement was particularly pertinent to the fish-scale
window panels of the curved roof which are an especially attractive
visual feature of the conservatory. The whole structure was finally
painted from top to bottom before glazing.
|
This
article is reproduced from The Building Conservation Directory, 1995
Author
GEOFFREY
WALLIS is a director
of Dorothea Restorations Limited, specialist restorers of historic
metalwork and machinery. Past projects have included the Water Lily
House in Kew Gardens; Bicton Palm House, Devon; cast iron roofs
in the Houses of Parliament and historic metalwork at the Jewel
House, Tower of London.
Dorothea Restorations Ltd are also traditional wind and water millwrights
of wide experience and suppliers of wrought, or 'puddled' iron for
specialist restoration work.
Further
information
|
RELATED
ARTICLES
Cold
Metal Stitching of Historic Metalwork
Wrought Ironwork
Wrought Iron and Conservation
RELATED
PRODUCTS AND SERVICES
Conservatories
Cast iron |
| |
© Cathedral Communications Limited 2005 |