The Limits of Lime
Repointing a damp church tower in the Hebrides
Paul Harding
| |
 |
|
| |
Our Lady, Star of the Sea stands high above the sea at Castlebay on the Hebridean island of Barra, and its tower
takes the brunt of the wind and rain |
|
It is generally held that if a solid stone
wall is pointed with a permeable lime
mortar, the high rate of evaporation from
its surface will limit rain penetration to just a
shallow surface layer. It would certainly never be
expected to reach the inner face.
However, there
have been a few recent cases on exposed sites
which have shown that this assumption cannot
be relied on. One of these is the category B
listed Victorian church of Our Lady, Star of
the Sea on the Hebridean island of Barra.
OUR LADY, STAR OF THE SEA
Barra is the most southerly inhabited island
of the Western Isles, lying west of the
Scottish mainland directly in the path of
frequent Atlantic gales. It has some of the
most extreme weather in the British Isles,
with very high average wind speeds and an
annual rainfall of about 1,100mm, almost twice
as much as London. The fact that the Gulf
Stream ensures that air temperature rarely
drops below freezing is little consolation.
The church faces the prevailing southwesterly
wind from an elevated site above the
village. Designed by George Woulfe Brenan, an
engineer and architect based in Oban, Our Lady,
Star of the Sea was completed in 1888, and has
squared walling of the local Lewissian gneiss with
ashlar dressings of imported Elgin sandstone.
Lewissian gneiss is a very hard metamorphic
rock which is difficult to work but has an
attractive range of colours from reddish-brown
through grey to black. This stone appealed to the
mainland Victorian architects and engineers who
used it widely on the island for constructing new
larger churches, schools and other buildings. The
choice was influenced by the Gothic Revival and
the tracts of Pugin and Ruskin. Very few of these
designers followed the traditional Scots practice
of coating walls with harling, the protective
mortar harled or hurled onto the wall which is
ideally suited to severe environmental conditions.
Damp problems have beset Our Lady,
Star of the Sea since it was first constructed.
The church consists of an arcaded aisled nave
with a square clocktower over the entrance
porch, where the heavy bell is supported
off walls built in three stages, thicker at the
porch than at belfry level, and buttressed
at the external corners. Only the tower
has this stepped section, and this is where
most of its damp problems originate.
The building had undergone a series of
earlier repairs. In the 1980s a major dry rot
outbreak resulted in most of the original
timber safe lintels (the innermost lintel over
an opening) being replaced together with
the boarded linings. The walls were then
repointed with cement-based mortar, and
coated with silane water repellent. How long
this coating lasted can only be guessed, but
it had no apparent effect. The tower walls
continued to leak so much that a system of
internal gutters and downpipes was installed
to try to intercept water inside the building:
these ran for several days after rain. Lime
leaching from the tower core created stalactite-like
deposits in sheltered areas inside and
out. The porch walls were very wet, and its
boarded linings were black with mould.
A programme of repairs was undertaken
on behalf of the RC Diocese of Argyll and the
Isles in 2004-2005. The approved project
included re-slating, new leadwork and
rainwater goods, as well as repointing the
whole building using lime-based mortar. The
scheme was grant-aided under the Listed
Places of Worship (LPW) programme, which
in Scotland is administered by the Heritage
Lottery Fund and Historic Scotland. The new
scheme provided the opportunity to remedy
the long-standing penetrating dampness
in the tower walls, but as the diocese was
informed, there could be no guarantee that the
penetrating damp would disappear completely.
There was, however, an expectation that the
problem would not be more acute afterwards.
ASSESSMENT AND SPECIFICATION
A thorough survey of the structure found the
stonework to be in very good condition, and
no indenting work was needed. Petrographic
analysis by the British Geological Survey
confirmed that the gneiss was extremely
impervious, eliminating the possibility
that moisture was getting in through the
stone. The focus of the repair work to the
tower walls was therefore on ensuring the
integrity of the mortar joints, and that
rainwater was properly shed from the roof.
Most pointing on the building was found
to be mechanically sound, and only at the
west gable and on the tower walling was it
cracked or not properly bonded. Because of
this, and since removing well-bonded cement
risked damaging the adjacent stonework,
especially the fine sandstone, Historic Scotland
agreed that sound areas should be left alone. Repointing was therefore largely confined to
the tower and west gable. In the tower joints
the residue of the original bedding mortar was
found to consist mainly of wet sandy granular
material, the result of lime leaching, under
20mm or so of cement mortar. Raking out
this material and tamping new mortar into
joints to an average depth of 150mm was a
requirement.
 |
 |
Before work commenced, the base of the tower was very wet and
the timber linings in
the porch were saturated and decaying |
A mason repoints the gneiss walling using a traditional, highly permeable hydraulic
lime mortar to a depth of 150mm |
The particular problems of the
tower, including the likelihood of water being
retained in intramural voids, had been reviewed at an earlier stage. The structural engineer
required that the tower wall was opened up
so the core could be inspected. He looked
into the possibility of grouting these voids but
considered that the exercise was likely to be an
expensive failure. He recommended repointing
using the appropriate NHL lime mortar for
the situation, also one of Historic Scotland’s
requirements. The Scottish Lime Centre then
undertook sampling and laboratory research,
including determining the original mortar mix
and composition. It set out recommendations
for the new mortar to be used, which were then
agreed with Historic Scotland.
The original
mortar mix was found to contain locally burnt
shell lime and beach sand which has
a high proportion of rounded particles, and
was considered unsuitable for pointing the
masonry. Another conclusion was that the
church had probably leaked since it was built,
and photographs taken shortly after it opened
showed much lime staining of the masonry.
The main reference documents for
repointing work at the time the project was
specified were Technical Advice Note (TAN) 1
‘Preparation and Use of Lime Mortars’
published in 1995 by Historic Scotland (1) and an
English Heritage study of remedial methods
used to combat dampness in west country
churches, published in 1989.(2) TAN 1 sets out
the technical case and recommendations for
the use of lime-based mortars, particularly in
buildings constructed of dense impervious
stone.(3) The English Heritage study compared
alternative remedies for impervious stonework
and concluded that repointing with an NHL
(hydraulic lime)-based mortar was the best
solution where walls could not be rendered.(4)
WORK ON SITE
Using a traditional lime mortar in this remote
island site required good organisation.
There was no local contractor with adequate
knowledge of this type of work and
therefore a suitably experienced off-island
stonemasonry firm was employed as the
masonry subcontractor. Although the lime
itself was to be provided ready-prepared, the
mason required the local main contractor’s
men to help him undertake some of the basic
preparatory work. The enthusiastic main
contractor enrolled himself and his men on a
specialist lime mortar training course on the
mainland to familiarise themselves with this
material, which is rarely used on Barra. They
all received commendations for their work.
It was hoped that the project would result in
more local familiarity and acceptance of lime
work, providing greater community benefit.
Lime work would require more frequent
inspection than the architects could provide,
so a very experienced retired surveyor was
interviewed and appointed as a Clerk of Works
by the diocese. It seemed that the stage was set
as well as it could be to suit this island project.
Some internal work began on site in late
2004 but hurricane-force winds in January 2005
caused long delays as the contractor was fully
occupied with emergency repairs elsewhere.
The scaffolding was finally erected in May 2005.
As work progressed it became clear that the
thicker tower walls would take a very long time
to dry out, even if the repointed walls succeeded
in reducing water ingress. But the wall at the
south aisle arcade grew significantly damper: the
gloss painted stone pilaster and arch blistered,
and unsightly stains appeared on the framed
plasterboard and timber lining. These areas
are of course very visible to worshippers.
The
porch contains the war memorial, a copper
wall plaque fixed to the timber lining, so had to
be kept as dry as possible. The priced proposal
had been for an independent framed wall and
ventilated cavity, reducing the porch’s already
small area. On Barra external vents can let in
wind-driven rain, so ventilation had to be to
the interior, which inevitably would become
more humid from the wet walls.
After the
decision to reduce the extent of repointing,
with Historic Scotland’s approval a proprietary
drained tanking system was introduced. This
kept the original porch floor area and allowed
a new flagstone floor to be laid in place of
slippery and unsightly 1980s tiles; the contractor
completed the work without affecting contract
period or overall cost. The fact that moisture
cannot now evaporate from the porch walls
is unlikely to have caused the increased
dampness on the nave side, as the rubble wall
core provides a multiplicity of routes for damp
percolating eventually into the sandy sub-floor.
PERSISTENT DAMP IN THE FINISHED WORK
The specified remedial work using lime-based
mortar followed established best practice, but
without success: damp still affects the same
walls. What went wrong? With hindsight it
seems that the particular circumstances of
the building have thwarted the best intentions
of all involved. It has of course been a very
frustrating experience for everyone.
| |
 |
| |
The tower wall from the south aisle after completion:
damp persists, damaging the new paintwork and
timber linings |
Originally it was suspected that failures in
the leadwork at the roof/tower junction and in
the nearby roof drainage were making a decisive
contribution to the damp problems below.
Unfortunately, delays in remedying these defects
delayed a clearer diagnosis.
Water seepage is
now present in the middle and lower stages
of the tower but not at the thinner top stage,
where the renewed and realigned parapet gutter
keeps the wallhead dry. This means that neither
the roof nor the sandstone ashlar facings and
projecting machicolations (the ornamental row
of small corbelled arches) below the parapet
level are likely to be the source of dampness in
lower walls, and this conclusion is supported
by the fact that sandstone elements elsewhere
do not appear to conduct water into the
interior except at the relatively thin window
reveals.
There is of course more surface water
running over the sandstone from adjacent
walling than if the building was made entirely of
sandstone, but (as in the cement-mortar pointed
remainder) it does not appear to be a significant
factor in the tower walls. The damp source is
clearly the repointed gneiss tower walling.
The next question was whether the
new mortar was exactly as specified, but
after opening up it was found to be correct
and well-carbonated. This confirmed
that in this instance the established
method of repair was itself at fault.
PRELIMINARY CONCLUSIONS
The tower walls’ construction can be
summarised as follows: it is largely made of
impervious stone; in the lower stages between
the two masonry skins there is a relatively
wide zone of backfilled random rubble where
the original bedding mortar has degraded
to sand, leaving occasional voids; there are
impermeable bonding stones tying the two
skins together, including those of the diagonal
buttresses; and the outer walling is now
pointed with a well tamped hydraulic lime
mortar to almost the full depth of the joints.
Since the walls continue to admit moisture
despite the porosity and depth of the new
mortar, the assumption made in authoritative
technical papers is not correct: in extreme
environments the rate of moisture evaporation
from the surface of a lime mortar joint is not
sufficient to keep the structure dry. This may
be because there are significant air pressure
differences between the exterior and interior
over much of the year, and between different
sides of the tower. Rainwater pushed through
the porous joints by strong wind remains in the
core, either in voids or in the degraded mortar,
transforming it into a sponge, and which air
pressure differences then pump into the interior.
Rainwater is also able to percolate out along the
repointed external joints much more than it
could with the previous cement pointing, and it
is leaching out lime, disfiguring the masonry.
 |
|
| The tower from the south showing the entrance to the
porch at the base of the tower |
|
In an environment like this where a
masonry wall is constructed of an impervious
stone and is pointed with a lime mortar, one
solution would be to introduce a lime-based
overcoat (harling or render), as this would
dramatically increase the area available
for surface evaporation. But the church’s
appearance could not be altered: its listing
means that its character is protected by law.
Another option would have been to grout
the core of the wall, and it may have been
premature to dismiss this option. However,
the engineer’s assumption of failure was
based on his experience of similar masonry
structures in similar environmental conditions,
and there are other well known examples
where grouting has been tried and failed,
as in the case of some Norfolk flint towers.
Furthermore, grouting is not reversible, and
this alteration would not have been supported
by Historic Scotland without further research.
For a project like this, where the
scale of the work is very limited, it is
not possible to undertake case-centred
research prior to embarking on the scheme,
and so the true nature of the problem
may not be understood before work is
irreversibly committed or complete.
With Historic Scotland’s approval a line has
been drawn under the project. Nevertheless,
with the evident failure of the pointing to keep
wind-driven rain out of the interior, if more
effective remedial action is to be taken, then
more (possibly expensive) work will be needed.
Finding a successful approach will require a
careful review of realistic options, and a firm
recommendation based on evidence. Any
alteration to this listed building will need to
be justified both to the client and to Historic
Scotland, as will further financial outlay.
THE WAY FORWARD
Penetrating dampness in historic masonry
structures of all kinds is not uncommon, and
from the evidence of several other Scottish
churches, it seems that chronic penetrating
damp often persists even after repointing
with lime mortar. Published guidance for
professionals dealing with such situations
does not adequately cover the problem
and may need to be reviewed. Research is
long overdue into the precise causes, the
mechanisms involved, and the alternative
specification options – particularly where it is
not possible to introduce an external render
or harling of lime mortar. Until then, the
difficulties and disappointments are likely to
continue. However, help may be at hand.
Over the past seven years English Heritage’s
Damp Towers Project has undertaken the only
significant research in this area, working with
Oxford and Sheffield Hallam universities.
The research takes forward the 1980s study
into rain penetration in West Country church
towers by examining a group of exposed church
towers in Devon and Cornwall that suffer from
penetrating damp, and by assessing the remedial
methods adopted in similar grant-aided repair
schemes. Research is nearing completion,
lab work has finished and English Heritage is
currently reviewing case studies and inspecting
towers that were repaired many years ago. This
work is expected to be completed by April
2011. When it is published it should go some
way to provide the research data we need.
From preliminary information there
seems to be evidence to support grouting in
cases where render or harling is not an option,
provided the wall construction is suitable.
| |
 |
| |
A detail of one
of the buttresses: Less than five years after repointing,
lime is leaching out of the mortar once again |
A third option subsequently considered
for Our Lady, Star of the Sea is to provide
a continuous damp proof course through
the tower walls using the same construction
method as underpinning. This would ensure
that water percolating down through the core
of the tower wall could at least be collected
and drained. However, this option presents
considerable technical challenges, and
since the masonry would remain saturated,
it would not provide a suitable solution
for buildings exposed to severe frosts.
Inevitably there are technical and cost
issues to be resolved with all such proposals,
and as no two buildings are the same, there
is a strong case for some building-centred
research to investigate the best option.
In the interim, until a definitive answer
can be agreed, the diocese has specified minor
work including a ventilated strapped lining
for the aisle wall and removing the remaining
built-in timber in the tower wall. This will
help to alleviate or avoid more problems,
but the damp walls will remain until an
effective treatment can be found. Stripping
the paint (which is non-original) from the
affected stone to allow evaporation will also
help, although there will be some minor
implications for comfort and heating costs.
Repair projects such as this are inevitably
of great local importance. The church building
is the focus and symbolic heart of many rural
communities which often have few resources
except enthusiasm. The efforts made to
organise the project and raise funds to allow
it to proceed cannot easily be repeated, but
somehow funds for further work will need
to be found. Our Lady, Star of the Sea could
provide an example of how to resolve a difficult
problem affecting many similar buildings.
~~~
Note
The stonework repair project at the Church
of our Lady, Star of the Sea, Castlebay was
funded by the Listed Places of Worship
programme, which is administered by the
Heritage Lottery Fund and Historic Scotland.
References
(1) Preparation and Use of Lime Mortars:
Technical Advice Note 1, Historic Scotland,
1995
(2) Rain Penetration in West Country Church
Towers, English Heritage Research
Technical and Advisory Services, 1989
(3) ibid, pp 3, 26
(4) ibid, Part 4 Conclusions and
Recommendations, para 4.7
|
|
This article was first published in Historic Churches 2010
Author
PAUL HARDING RIBA ARIAS FRSA is a partner with
Benjamin Tindall Architects based in Edinburgh. He
has worked with historic
buildings for over 30 years, including many buildings in the Western Isles and the Orkney
Islands. For 15 years he was technical advisor to the
Edinburgh Old Town Renewal Committee and the
Edinburgh World Heritage Trust.
Email
paul@benjamintindall
architects.co.uk
Further
information
RELATED
ARTICLES
Churches (general)
Lime Mortars and Renders
RELATED
PRODUCTS AND SERVICES
Lime, hydraulic
Lime, hair & fibre reinforcements
Lime, non-hydraulic (lime putty)
Lime pointing
Lime, pointing tools
Lime, pozzolanic additives
Limewash
DAMP TOWERS PROJECT
English Heritage’s
Damp Towers Project, which was carried out with
Oxford and Sheffield Hallam universities, has now been completed and the results of the research are to be presented at a conference in Autumn 2012. Further details will be published in the 2012 edition of Historic Churches and on this website.

Site Map
© Cathedral
Communications Limited 2012
|