Table of Contents Table of Contents
Previous Page  36 / 62 Next Page
Information
Show Menu
Previous Page 36 / 62 Next Page
Page Background

36

BCD SPECIAL REPORT ON

HISTORIC CHURCHES

24

TH ANNUAL EDITION

large diameter iron bars with large

pattress plates on the outside to anchor

them. The current practice is to use

bespoke stainless steel ties such as Cintec.

These are drilled through the full breadth

of each face of the tower from corner to

corner and grouted in place. The core

from the facing stone is then re-fixed,

leaving an almost invisible repair. The

positioning of these ties depends on the

configuration of the tower, but generally

they are positioned above the openings in

the walls at each level.

Some towers develop cracks in the

window reveals. These are more serious,

indicating that the wall thickness is

spreading due to the rubble fill in the

centre of the wall consolidating and

pushing the two masonry faces apart.

These cracks are quite common in flint

towers where the rounded flints in the

centre of the wall can move more easily

and wedge down into gaps between the

flints below, pushing the faces apart.

Spreading is likely to worsen with

continued bell ringing.

Through-thickness tying can be used

where there are stone or brick facings and

the cores can be grouted with a fluid lime

mortar grouting. Flint walls can be more

problematic due to the difficulty of coring

– drilling out the tie holes with a hollow

cylindrical bit – and the smaller size of

each flint. The Society for the Protection

of Ancient Buildings recommends cutting

pockets through the wall and building

in stainless steel mesh ties (see Further

Information), but this may be difficult to

achieve in practice.

NEW FOUNDATIONS

FOR BELL FRAMES

Occasionally, there is a requirement to

install a bell frame in a tower which has

not previously had full-swing bells. More

commonly, there is a requirement to

change the level of a bell frame. In both

cases it is first necessary to establish how

to install the bell frame while following

sound conservation principles.

In the mid-20th century, square

concrete rings were often cut into and

embedded in the internal faces of the

tower with either a concrete floor or

integral transverse beams supporting

the bell frames. This approach leads to

significant loss of original fabric and

would be difficult to reverse without

causing extensive damage to the original

masonry, particularly when breaking out

the embedded concrete.

Nevertheless, the concrete ring

serves the fundamental function of

holding the four sides of the tower

together and spreading the forces from

the bell ringing more uniformly into

the walls. To retain these benefits while

minimising loss of fabric, one option is

to construct the reinforced concrete ring

beam adjacent to the inside face of the

tower and tie it to the walls by a series

of stainless steel anchor bars grouted

into 150mm diameter pockets cored into

the walls at regular intervals. If removal

were required, the ring beam could be

cut using vibrationless methods such as

diamond sawing and the anchors in the

wall could be cored out.

MONITORING FOLLOWING

CHANGES TO THE BELL FRAME

From the viewpoint of the bell ringers,

there is nothing to be gained by

monitoring after the changes have

taken place. However, by improving our

understanding of the behaviour of these

structures there is much to be learned.

The interaction between full swing

bells and bell towers is complex. The

forces are significant and all bell towers

move. The bell frames on which the bells

are mounted distort as the bells swing

and they are jerked when an adjacent bell

swings. Not only can these forces make

ringing difficult, but they can also be

highly destructive.

Monitoring can be used to identify

where movement is occurring and

may demonstrate that there is no

need for major changes if the frames

can be tightened up. Monitoring

can also show the movement shape

of the tower and the distortions of

the walls. However, monitoring will

not be able to determine how the

movement of the tower will change for

any given alterations to the frames.

With time, if sufficient pre- and post-

alteration monitoring is carried out, a

better understanding may develop. Harry

Windsor was undertaking this work

when he died. His work was voluntary,

my own is commercial. As a practising

structural engineer, I have found bell

ringers reluctant to fund work which

gives them no direct benefit and I have

not been called back to carry out post-

alteration monitoring. Until we have the

opportunity to carry out the ongoing

monitoring required, advising on the

impact of changing bell frames will

remain more an art than a science.

Further Information

AP Heywood,

Bell Towers and Bell

Hanging: An Appeal to Architects

,

Longmans & Co, London, 1914

D Lodge and A Wright,

Care and

Repair of Flint Walls

, SPAB Technical

Pamphlet 16, 2000 (see fig 8)

D Robinson and H Windsor,

A Practical

Analysis of the Interaction Between

Church Bells and Towers

, The Central

Council of Church Bell Ringers, 1994

R Smith and H Hunt, ‘Vibration of Bell

Towers Excited by Bell Ringing: a

new approach to analysis’, Cambridge

University Engineering Department,

Cambridge, 2008 (www2.eng.cam.

ac.uk/~hemh1/isma2008.pdf

)

H Windsor,

Further Analysis of the

Interaction between Church Bells and

Towers

, The Central Council of Church

Bell Ringers, 2007

ANDREW DUTTON

MA(Cantab) CEng

FICE FIstructE (

adutton@hurstpm.co.uk)

is a consulting engineer with Hurst Peirce

& Malcolm consulting structural engineers.

He is an accredited conservation engineer

under the CARE scheme and he specialises in

historic buildings, including church towers in

south east England.

This typical new bell frame foundation with a concrete ring beam inside the tower

walls was installed at All Saints, Fulham (see page 33).

A typical anchor tie into the wall