Table of Contents Table of Contents
Previous Page  34 / 62 Next Page
Information
Show Menu
Previous Page 34 / 62 Next Page
Page Background

34

BCD SPECIAL REPORT ON

HISTORIC CHURCHES

24

TH ANNUAL EDITION

Timber bell frames were usually

mounted on timber foundation girders,

spanning across the tower but they

may have been replaced with steel

beams at some stage. The timber bell

frame foundation girders are usually

of substantial proportion but they will

still flex a little and they can also slip

in and out of the sockets in the walls.

Steel foundation beams are more flexible

and need to be substantially braced

to limit their flexing. In one church,

where a timber frame was mounted in

three parallel but unbraced steel beams,

the beams were found to be flexing

by over 6mm laterally during some

ringing sequences. The anchorages of

the steel beams in the walls can also be

problematic with hammering occurring.

The tower itself can be considered

as an elastic structure which will move

under the forces induced by bell ringing.

Ideally it will act as a single box which is

very stiff. However, there are normally

weaknesses in the walls of the tower in

the form of window and sound louvre

openings and it is not uncommon to

find vertical cracks running down the

centres of each wall from opening to

opening. These cracks effectively reduce

the stiffness from that of a box with a side

of ‘x’ to four angles with a side of half ‘x’,

which are therefore much less stiff. In

a sense, the action of the bell ringing is

trying to reduce the stiffness of the tower

to this lower state by increasing the size of

the cracks. The natural frequency of the

tower will change as the cracks develop.

Cracks can also develop in the

window reveals, indicating that the wall

thickness is spreading as the rubble fill

in the walls is shaken down. This is a

particular problem in flint towers.

While the bells are rung to a rhythmic

sequence, their different orientation

and the ringing changes mean that

the imposed forces do not rise and fall

smoothly in a simple sine wave, but result

in a series of jerks as each bell swings.

On occasions this can produce a sequence

of pulses which briefly match the natural

frequency of the tower.

MONITORING

With careful monitoring, it should

be possible to differentiate between

the movements of the bell frame, the

movements of the foundation beams

and the movement of the tower at

different levels. This requires measuring

movement in each of these three elements

simultaneously. From the three sets of

data it will be possible to discover what

portion of the total movement of the

top of the bell frame (and hence the

difficulty to ring) is due to slackness in

the bell frame, sway in the foundation

beams below, and sway in the tower as a

whole. The bell ringers can then assess the

benefits to be gained from various levels

of improvement.

It could easily be the case that a

50 per cent reduction in the movement

at the bell pivots can be achieved by

improvements to a timber bell frame,

whereas the more expensive option of

installing new foundation beams might

only give a 10 per cent improvement.

Similarly, the even more expensive option

of lowering the bell frame in the tower

to reduce sway itself may give only a

very small improvement and, for reasons

which will be discussed later, could even

result in greater movement.

Monitoring can take many forms

depending on what is being sought.

A finger placed across a crack running up

the centre of the wall during ringing will

be sensitive enough to feel whether the

crack is ‘working’ (opening and closing).

To determine the benefit of tightening up

a timber frame or replacing it with a metal

frame, it is possible to install temporary

wedging and blocking between the

frames and the walls so they cannot move

differentially to the tower. This is only a

temporary expedient, however, because

potential hammering as the wedges

loosen can damage the masonry.

Ideally, accurate electronic

measurement of all elements

simultaneously will yield the most

information. Electronic measurement of

bell frame movement was developed by

the late Harry Windsor of the Central

Council of Church Bell Ringers when

it became apparent that a lowered

bell frame had resulted in increased

movement in one church tower. Windsor

produced a publication on his method

of monitoring and his assessment of why

the movement might have increased,

based on the harmonics of the bell ringing

matching the natural frequency of the

tower. He was about to publish a revision

to his booklet when he died in 2007

(see Further Information, Windsor).

Windsor’s method of monitoring

employed accelerometers mounted

on the bell frames and tower with

a data logger. The accelerometer

information then had to be transferred to

spreadsheets for the actual displacement

to be calculated by the mathematical

process of double integration, a slow and

tedious process.

At this time I was developing my own

electronic system which automatically

calculated displacements from the

accelerations and simultaneously carried

out the data integration as a continuous

process, allowing instant plots of the

movement. Three accelerometers, each

able to measure the acceleration in the

x and y directions simultaneously, could

This plot shows the movement in the north and south walls of the bell chamber

when all bells oriented east-west (the Y axis) are rung simultaneously, producing

a large pulse. The effect on the tower is captured by accelerometers attached to

the masonry of the north and south walls of the bell chamber. The pulse leads to a

jerk on the east-west axis (yellow and green lines) which is much longer than the

natural frequency of the tower which is just over 2Hz.

A comparison between the movement of the frame on the north-south (X) axis

in red, and the much smaller movement of the south wall (blue) on the same

axis. This shows the considerable benefit which can be achieved by stiffening up

the frame.

PLOT A: Bells ‘firing’ east-west simultaneously, with accelerometers on

north and south walls of bell chamber

PLOT B: Bells ‘firing’ north-south simultaneously, with accelerometers on

bell frame and on south wall of bell chamber